Construction Timeline
Stage 1
- April 2019 - Site preparation and tree removal as part of endorsed arborist plans
- Mid 2019 - Piles completed & ground floor slab underway
- Late 2019 - Level 4 slab & roof steel structure completed
- Mid 2020 - Façade completed
- Late 2020 - Fit-out completed
Stage 2
- Late 2020 - Car parking and landscaping, including planting 80 mature trees and 35,000 tube stock