Costs and Funding

Costs

Stage 1 - Construction: $47.4m (excluding GST)

Stage 2 - Landscaping, car parking, specialist equipment: $2.5m (excluding GST)

Funding

Funding for the build came from:

  1. $15.35m – Greater Shepparton City Council
  2. $10m – State Government
  3. $15m – Federal Government
  4. $7m – SAM Foundation

Council is seeking funding for Stage 2 of the project and is exploring grant options from State and Federal governments.