Construction

Construction Timeline

Stage 1

  • April 2019 - Site preparation and tree removal as part of endorsed arborist plans
  • Mid 2019 - Piles completed & ground floor slab underway
  • Late 2019 - Level 4 slab & roof steel structure completed
  • Mid 2020 - Façade completed
  • Late 2020 - Fit-out completed

Stage 2

  • Late 2020 - Car parking and landscaping, including planting 80 mature trees and 35,000 tube stock