New Shepparton Art Museum - Project Update for October

Work is progressing well with Level two deck poured and Level three almost ready for the next concrete pour.

Construction works completed:

  • Level 2 verticals (columns and core walls)
  • Level 2 concrete deck poured
  • Electrical substation energized
  • Demolition of the Caravan Park Residences

Construction works commenced:

  • Internal Sewer Infrastructure
  • Loading dock vertical walls formwork and pour

Construction works coming up:

  • Level 3 formwork and concrete pour
  • Level 3 vertical formwork and concrete pour

Kane Constructions are employing staff, contractors and businesses from the region to work on the new art museum. The most recent interviewees were:

  • Contract Administrator and Green Star professional, James Wimbridge from Shepparton
  • Health and Safety Representative, Doug McDonald from Cobram

For the latest time lapse video, photos and update videos please visit the new SAM project web page.

 