New Shepparton Art Museum - Project Update for September

The first level concrete pour was completed on 19 September with 400 cubic metres of concrete and 10 tonne of steel involved.

Construction works completed:

  • Ground floor services and concrete
  • Building core and column verticals
  • Level 1 concrete deck

Construction works commenced:

  • Stormwater drainage

Construction works coming up:

  • Demolition of the caravan park residence
  • Level 2 formwork and concrete pour 
  • Level 2 vertical formwork and concrete pour 
  • Loading dock vertical walls formwork and pour

For the latest update video please visit the new SAM project web page

 