Works at GV Link Enterprise Park reaching milestones
Posted on
Friday 19th of December, 2025,
Works at GV Link Enterprise Park, at 250 Toolamba Road, Mooroopna, continue to progress, with Stage 1 of the roundabout works nearing completion and the subdivided lots taking shape.
Works at the site commenced in April, with Greater Shepparton City Council and contractor BMD Urban, making good progress on Stage 1. This stage involves:
A four-lot industrial subdivision across a 55-hectare site – the equivalent size of 28 MCG playing fields
Upgrade to a roundabout at the intersection of Toolamba Road and Simson Road, and
Utility service connections to Mooroopna, including gas, sewer, water and NBN.
Bulk earthworks across the four lots are nearing completion. Works along Simson Road and Innovation Drive – a new road through the subdivision – are well underway, along with construction of the site’s wetland.
Stage 1 of the roundabout is now structurally complete, with asphalt works planned for January 2026. Stage 2, which involves works alongside the railway line, is scheduled to commence in late January, which will result in a change of traffic conditions to enable the Stage 2 works to be completed.
Utility service connections have also progressed well, with works through the Mooroopna township now complete. Connections towards Rumbalara Road are expected to be finished before Christmas, while works further along Toolamba Road, towards the Mooroopna Police Station and across the Midland Highway, will continue in early 2026.
Mayor, Councillor Shane Sali, thanked the community for their patience and understanding while works have been undertaken.
“We understand the significant impact these works have had on traffic flow in the area. We appreciate the community’s patience while construction has been underway and traffic diversions have been in place,” he said.
“The team have made great progress on site this year. GV Link Enterprise Park will support greater investment in our region, paving the way for future development stages, new industry and key projects.
“It’s fantastic to see strong partnerships with local businesses and community groups maintained throughout the works, ensuring shared benefits and economic growth for Greater Shepparton.”
Several local community groups have already benefited from the project, receiving a share of the timber recovered from the bulk earthworks. The Dookie United Football Netball Club and Mooroopna Men’s Shed have received felled large timber for their community fundraising initiatives, while the Goulburn Broken Catchment Management Authority has also received large root balls to support native fish habitat recovery.
BMD Urban Regional Operations Manager, Greg Stevens, said significant local supplier investment was a hallmark of the project.
“We have approximately 30 local - small to medium - enterprises involved in the construction, which was a commitment from BMD Urban that is being delivered. We are proud to be supporting local suppliers to deliver a project that creates jobs and opportunities for Greater Shepparton,” he said.
Works on site will pause over Christmas, with after-care traffic management remaining in place. Construction will recommence in January, with Stage 1 of GV Link Enterprise Park expected to be completed by the end of April 2026.
To find out more about GV Link Enterprise Park, for recent photos of the works or to subscribe for project updates, visit the Major Projects Page.
Posted on Friday 19th of December, 2025,
Works at GV Link Enterprise Park, at 250 Toolamba Road, Mooroopna, continue to progress, with Stage 1 of the roundabout works nearing completion and the subdivided lots taking shape.
Works at the site commenced in April, with Greater Shepparton City Council and contractor BMD Urban, making good progress on Stage 1. This stage involves:
Bulk earthworks across the four lots are nearing completion. Works along Simson Road and Innovation Drive – a new road through the subdivision – are well underway, along with construction of the site’s wetland.
Stage 1 of the roundabout is now structurally complete, with asphalt works planned for January 2026. Stage 2, which involves works alongside the railway line, is scheduled to commence in late January, which will result in a change of traffic conditions to enable the Stage 2 works to be completed.
Utility service connections have also progressed well, with works through the Mooroopna township now complete. Connections towards Rumbalara Road are expected to be finished before Christmas, while works further along Toolamba Road, towards the Mooroopna Police Station and across the Midland Highway, will continue in early 2026.
Mayor, Councillor Shane Sali, thanked the community for their patience and understanding while works have been undertaken.
“We understand the significant impact these works have had on traffic flow in the area. We appreciate the community’s patience while construction has been underway and traffic diversions have been in place,” he said.
“The team have made great progress on site this year. GV Link Enterprise Park will support greater investment in our region, paving the way for future development stages, new industry and key projects.
“It’s fantastic to see strong partnerships with local businesses and community groups maintained throughout the works, ensuring shared benefits and economic growth for Greater Shepparton.”
Several local community groups have already benefited from the project, receiving a share of the timber recovered from the bulk earthworks. The Dookie United Football Netball Club and Mooroopna Men’s Shed have received felled large timber for their community fundraising initiatives, while the Goulburn Broken Catchment Management Authority has also received large root balls to support native fish habitat recovery.
BMD Urban Regional Operations Manager, Greg Stevens, said significant local supplier investment was a hallmark of the project.
“We have approximately 30 local - small to medium - enterprises involved in the construction, which was a commitment from BMD Urban that is being delivered. We are proud to be supporting local suppliers to deliver a project that creates jobs and opportunities for Greater Shepparton,” he said.
Works on site will pause over Christmas, with after-care traffic management remaining in place. Construction will recommence in January, with Stage 1 of GV Link Enterprise Park expected to be completed by the end of April 2026.
To find out more about GV Link Enterprise Park, for recent photos of the works or to subscribe for project updates, visit the Major Projects Page.
More News from Greater Shepparton
Monday 2nd of February,
Sod turned on new Princess Park WB Hunter Pavilion
The first sod was officially turned on the new Princess Park WB Hunter Pavilion today, marking the beginning of the new facility which will serve generations of grassroots sporting players and supporters to come. Read more
Friday 30th of January,
Works to begin in Shepparton Inner North - Local Area Traffic Management Project
Council wishes to advise that works will be undertaken in early February 2026 in Shepparton Inner North as part of the Local Area Traffic Management Project. Read more
Friday 30th of January,
Help shape Council’s Universal Access and Inclusion Plan 2026-2030
Greater Shepparton City Council is developing its new Universal Access and Inclusion Plan for 2026-2030 and is seeking community input to ensure Greater Shepparton remains inclusive and accessible for everyone. Read more
Tuesday 27th of January,
2026 Greater Shepparton Australia Day Awards winners
The winners of the 2026 Greater Shepparton Australia Day Awards were announced on Monday 26 January 2026 at ceremonies across Greater Shepparton. Read more
Thursday 22nd of January,
Blue-green algae levels decline in Lake Bartlett
Greater Shepparton City Council advises that the blue-green algae warning for Lake Bartlett in Tatura has been removed, following a significant decline in blue-green algae levels. Read more
Thursday 22nd of January,
Join the Greater Shepparton Heritage Advisory Committee
Greater Shepparton City Council is welcoming nominations from individuals interested in joining the Greater Shepparton Heritage Advisory Committee. Read more
See All News
Want to get the latest news and events in your Facebook feed?
Just go to our Facebook page and click the Like button.
More Events in Greater Shepparton
Tuesday 3rd of February,
Aqua Aerobics
Looking for a fun way to stay fit and cool this summer? Read more
Saturday 7th of February,
Pedal Boats
Looking for a relaxing way to enjoy the water? Read more
Friday 6th of February,
Puff Walk
Puff Walks are more than just steps – they’re connections. Read more
Saturday 7th of February,
Stand Up Paddle Boarding
Make your next outing unforgettable with a stand‑up paddleboarding session. Read more
Monday 9th of February,
Family History Chat at Shepparton Library
Family history buffs come and chat! Read more
Sunday 8th of February,
Aqua Aerobics
Looking for a fun way to stay fit and cool this summer? Read more
See All Events