Works at GV Link Enterprise Park reaching milestones
Posted on
Friday 19th of December, 2025,
Works at GV Link Enterprise Park, at 250 Toolamba Road, Mooroopna, continue to progress, with Stage 1 of the roundabout works nearing completion and the subdivided lots taking shape.
Works at the site commenced in April, with Greater Shepparton City Council and contractor BMD Urban, making good progress on Stage 1. This stage involves:
A four-lot industrial subdivision across a 55-hectare site – the equivalent size of 28 MCG playing fields
Upgrade to a roundabout at the intersection of Toolamba Road and Simson Road, and
Utility service connections to Mooroopna, including gas, sewer, water and NBN.
Bulk earthworks across the four lots are nearing completion. Works along Simson Road and Innovation Drive – a new road through the subdivision – are well underway, along with construction of the site’s wetland.
Stage 1 of the roundabout is now structurally complete, with asphalt works planned for January 2026. Stage 2, which involves works alongside the railway line, is scheduled to commence in late January, which will result in a change of traffic conditions to enable the Stage 2 works to be completed.
Utility service connections have also progressed well, with works through the Mooroopna township now complete. Connections towards Rumbalara Road are expected to be finished before Christmas, while works further along Toolamba Road, towards the Mooroopna Police Station and across the Midland Highway, will continue in early 2026.
Mayor, Councillor Shane Sali, thanked the community for their patience and understanding while works have been undertaken.
“We understand the significant impact these works have had on traffic flow in the area. We appreciate the community’s patience while construction has been underway and traffic diversions have been in place,” he said.
“The team have made great progress on site this year. GV Link Enterprise Park will support greater investment in our region, paving the way for future development stages, new industry and key projects.
“It’s fantastic to see strong partnerships with local businesses and community groups maintained throughout the works, ensuring shared benefits and economic growth for Greater Shepparton.”
Several local community groups have already benefited from the project, receiving a share of the timber recovered from the bulk earthworks. The Dookie United Football Netball Club and Mooroopna Men’s Shed have received felled large timber for their community fundraising initiatives, while the Goulburn Broken Catchment Management Authority has also received large root balls to support native fish habitat recovery.
BMD Urban Regional Operations Manager, Greg Stevens, said significant local supplier investment was a hallmark of the project.
“We have approximately 30 local - small to medium - enterprises involved in the construction, which was a commitment from BMD Urban that is being delivered. We are proud to be supporting local suppliers to deliver a project that creates jobs and opportunities for Greater Shepparton,” he said.
Works on site will pause over Christmas, with after-care traffic management remaining in place. Construction will recommence in January, with Stage 1 of GV Link Enterprise Park expected to be completed by the end of April 2026.
To find out more about GV Link Enterprise Park, for recent photos of the works or to subscribe for project updates, visit the Major Projects Page.
Posted on Friday 19th of December, 2025,
Works at GV Link Enterprise Park, at 250 Toolamba Road, Mooroopna, continue to progress, with Stage 1 of the roundabout works nearing completion and the subdivided lots taking shape.
Works at the site commenced in April, with Greater Shepparton City Council and contractor BMD Urban, making good progress on Stage 1. This stage involves:
Bulk earthworks across the four lots are nearing completion. Works along Simson Road and Innovation Drive – a new road through the subdivision – are well underway, along with construction of the site’s wetland.
Stage 1 of the roundabout is now structurally complete, with asphalt works planned for January 2026. Stage 2, which involves works alongside the railway line, is scheduled to commence in late January, which will result in a change of traffic conditions to enable the Stage 2 works to be completed.
Utility service connections have also progressed well, with works through the Mooroopna township now complete. Connections towards Rumbalara Road are expected to be finished before Christmas, while works further along Toolamba Road, towards the Mooroopna Police Station and across the Midland Highway, will continue in early 2026.
Mayor, Councillor Shane Sali, thanked the community for their patience and understanding while works have been undertaken.
“We understand the significant impact these works have had on traffic flow in the area. We appreciate the community’s patience while construction has been underway and traffic diversions have been in place,” he said.
“The team have made great progress on site this year. GV Link Enterprise Park will support greater investment in our region, paving the way for future development stages, new industry and key projects.
“It’s fantastic to see strong partnerships with local businesses and community groups maintained throughout the works, ensuring shared benefits and economic growth for Greater Shepparton.”
Several local community groups have already benefited from the project, receiving a share of the timber recovered from the bulk earthworks. The Dookie United Football Netball Club and Mooroopna Men’s Shed have received felled large timber for their community fundraising initiatives, while the Goulburn Broken Catchment Management Authority has also received large root balls to support native fish habitat recovery.
BMD Urban Regional Operations Manager, Greg Stevens, said significant local supplier investment was a hallmark of the project.
“We have approximately 30 local - small to medium - enterprises involved in the construction, which was a commitment from BMD Urban that is being delivered. We are proud to be supporting local suppliers to deliver a project that creates jobs and opportunities for Greater Shepparton,” he said.
Works on site will pause over Christmas, with after-care traffic management remaining in place. Construction will recommence in January, with Stage 1 of GV Link Enterprise Park expected to be completed by the end of April 2026.
To find out more about GV Link Enterprise Park, for recent photos of the works or to subscribe for project updates, visit the Major Projects Page.
More News from Greater Shepparton
Friday 19th of December,
Greater Shepparton to attend Asia Fruit Logistica in 2026
Greater Shepparton City Council will host a trade stand at Asia Fruit Logistica in Hong Kong in 2026, partnering with Fruit Growers Victoria (FGV), following positive outcomes from the 2025 delegation being noted at the December Council Meeting. Read more
Friday 19th of December,
Blue Green Algae warning for Lake Bartlett
Greater Shepparton City Council is warning the public to avoid direct contact with water in Lake Bartlett in Tatura after detecting high levels of blue-green algae. Read more
Wednesday 17th of December,
Council awards over $1.9 million in contracts for projects
Greater Shepparton City Council noted the awarding of more than $1.9 million in contacts for three projects at the December Council Meeting on Tuesday. These works include essential maintenance and projects which keep our region moving and residents… Read more
Wednesday 17th of December,
Council to establish Australian Botanic Gardens Shepparton User Group
Greater Shepparton City Council is pleased to advise the formation of the Australian Botanic Gardens Shepparton User Group. The formation was approved at Tuesday’s December Council Meeting following the decision to dissolve the Australian Botanic Gardens… Read more
Thursday 11th of December,
Council reminds residents to keep pets safe during summer
Greater Shepparton City Council is encouraging residents to take extra care of their pets as temperatures rise, with a reminder of the vital role responsible pet ownership plays in keeping animals healthy and comfortable throughout the summer months. Read more
Thursday 11th of December,
Council services over Christmas and New Year
With the jingle of Christmas just around the corner and a new year fast approaching, it’s time to take note of Council’s festive season hours. Read more
See All News
Want to get the latest news and events in your Facebook feed?
Just go to our Facebook page and click the Like button.
More Events in Greater Shepparton
Saturday 20th of December,
Body Balance in the Park
Move with ease Read more
Sunday 21st of December,
Mooroopna Market
Enjoy the Last Sunday morning of each month out at Mooroopna Market. Read more
Tuesday 23rd of December,
Santa on the Move: Shepparton CBD
Santa and his elves will be visiting various locations across Greater Shepparton this December. Take your own family photos with Santa, enjoy festive games, craft activities and face painting all for… Read more
Tuesday 6th of January,
Storytime and Nature Walk
Celebrate nature with us! Read more
Wednesday 7th of January,
Big Bash on the Big Screen @ Victoria Park Lake
A free summer evening by the lake with cricket activities live entertainment and the Big Bash match on the big screen. Bring a picnic rug round up your friends and enjoy a relaxed night out close to home. Read more
Saturday 20th of December,
'The Grinch' in The Paddock
Join us on the 20th of December in The Paddock to watch 'How The Grinch Stole Christmas' on the big screen! Tickets are $15 each, and children 12 and under are free. We will have popcorn, slushies, wood-fired… Read more
See All Events