The two remaining changeover dates have been scheduled as follows:
- Saturday 1 June 2019 from 9:30am to 2:30pm – traffic will be permitted in all directions at a restricted speed.
- Tuesday 4 June 2019 from 9:30am to 2:30pm – the roundabout will be closed to northbound traffic travelling from Hawdon Street with other traffic permitted at a restricted speed. Please refer to the attached traffic management plan.
Goulburn Valley Water will contact any properties whose water will be affected by these works in accordance with their customer service policy.
Access to properties will not be affected by these works.
Tenders for the additional water main replacement works required to accommodate the indented parking on Balaclava and New Dookie Roads are currently being advertised.
For more information visit the project page.