Marungi Street Drainage Project – Commencing Stage 2

Greater Shepparton City Council wishes to advise that the next stage of construction works to upgrade the stormwater drainage network along Marungi Street, Shepparton, will soon commence.

Following successful completion of stage 1 of the project, stage 2 works will begin on Monday 12 January 2026.

Traffic changes for stage 2 will be in place from Monday 12 January. Details of the closures are outlined in the table below and shown in image 1. Further updates on future works will be communicated in due course.

  Location of the work and community impact Anticipated timeframe
Stage 2
  • Nixon / Marungi Street Roundabout - eastbound from Marungi Street into Nixon Street – CLOSED.
  • Movement through the roundabout of Marungi Street and Nixon Street is available.
  • Marungi Street OPEN.
Approximately one to two weeks, pending construction progress.

Every effort will be made to maintain access to private properties throughout the construction period. Road users and pedestrians are reminded to observe all on site signage, detours and direction provided by traffic controllers during the works.

Due to unknown services, wet weather and unforeseen circumstances, project completion is now expected by the end of March 2026, weather permitting.

Council apologises for any inconvenience these works may cause and appreciates the community’s patience and co-operation.

For further information, contact Council’s Projects Delivery and Assets team on (03) 5832 9700 or email projects@shepparton.vic.gov.au

Keep up to date with the project by visiting our Major Projects page here. 

An image of the scheduled works area can be viewed on the right. 

 